Qatar Gas 3&4 LNG Onshore Facilities

Client: CTJV - JV of Chiyoda Corporation & Technip Ras Laffan, Qatar
Owner: Qatar Gas
Consultant Engineers: Conoco Phillips/Shell
Contract Value: USD 15,000,000
Period of Work: 15 Months - ending December 2010

Project scope: Pre-Mechanical Completion Works in the Utilities & Offsites Areas.

The Qatargas 3 (QG3) project involved the construction of a new LNG mega-train (Train 6) with a capacity of 7.8 MTA. QG 3 will produce 1.4 billion standard cubic feet of gas per day, delivering LNG and substantial volumes of condensate and LPG.

Major Scope and Quantities Include:

  • 250,000 ID of Piping
  • 1,500 Tons of Static & Rotating Equipment erection
  • 6,000 Tons of Steel Structure